Ofgem, the energy regulator, launched an urgent inquiry on Thursday 19 November 2026 into why so many projects waiting to connect to the electricity grid have been given later dates than they had before. It says “the majority of projects in the reformed queue are seeing delays rather than advancements”. Ofgem is also exploring automatic compensation for customers when a network company causes the delay. If your business is waiting on a new or bigger electricity connection, the first thing to do is get your dates and paperwork together, and we can help you with the supply contract that has to sit alongside it.
The facts
- Who: Ofgem. It says it is working with the Department for Energy Security and Net Zero.
- What: in Ofgem’s words, it is “launching an urgent inquiry into why grid connection offers for many protected and Phase 1 projects have been delayed” compared with the dates those projects were offered before the queue was reformed.
- Who it is looking at: the network companies and the National Energy System Operator (NESO), which monitors the queue. Ofgem has asked them to find ways to improve outcomes and bring dates forward.
- Enforcement: “Where this inquiry reveals a material breach of licence obligations”, Ofgem says, “we will not hesitate to take enforcement action”.
- Who leads it and when it reports: the announcement doesn’t say.
- How many projects: no number is given. The announcement doesn’t define “protected” or “Phase 1” projects either.
What went wrong?
The grid connection queue is the line of projects waiting to be connected, including batteries and data centres. It was reformed to clear out projects that were never likely to be built. Ofgem says that worked: the reform took a significant amount of speculative capacity out of the queue and left a more credible list.
The trouble is the dates. Most of the projects left in the queue have been moved back. Ofgem’s own words are: “We share the frustration of customers whose projects have moved backwards in the queue”.
It also sets out the scale of the job: “As a country, the amount we need to connect to the network is doubling every few years.”
What Ofgem says will change
Clearer information
- Dates shared: connection dates will be shared and updated as offers are issued, with changes explained.
- The working behind an offer: NESO will publish more about the planning assumptions it uses and, with the industry, propose changes to the queue rules.
- Money down: work is under way on financial commitments for technologies with more applicants than room, which Ofgem names as batteries, and for speculative and non-viable data centre projects.
- Milestones checked: NESO will monitor each project’s milestones and step in where a project isn’t making enough progress.
A better deal for the customer
- Compensation: “We are exploring stronger arrangements for automatic compensation to customers where networks cause delays to connections”. Ofgem adds that it can “see no reason why connection agreements cannot contain such provisions now”.
- Customer service: to be strengthened through its programme called Transforming the Connections Experience.
- Building it yourself: more room for developers to build their own transmission connection and hand it over, or to own the assets under an independent transmission owner licence.
Holding the networks to account
- Rewards and penalties: Ofgem plans to use the connections incentive in RIIO-3, its current rules for the network companies, to reward or penalise them on how they perform. “We will consult on setting the baseline for this incentive in December”.
- More reporting: it will report more often, “starting with the Infrastructure Progress Report in February where we will publish the data on connection outcomes”.
Ofgem says the test of all this is whether customers get better outcomes, “not simply a shorter queue”.
The questions worth asking
- Why did the dates slip after the queue was cleared? That is the question the inquiry has been set. There is no answer yet.
- When will it report? No date has been given.
- Who pays for compensation? Ofgem is “exploring” it. It hasn’t said how much, who qualifies, or whether the cost ends up in network charges on everyone’s bills.
- Does it reach smaller connections? The inquiry is about protected and Phase 1 projects in the reformed queue. The announcement doesn’t say what it means for a business asking its local network for a bigger supply.
- Will the networks be penalised? The baseline for the incentive is still to be consulted on in December.
What does this mean for your business?
- Waiting on a connection? Get the dates in writing. Keep the date you were first offered and every date since. If compensation for network delays comes in, that record is your evidence.
- Read your connection agreement for a delay clause. Ofgem says it sees no reason these agreements can’t provide for compensation now. If you’re about to sign one, ask for it.
- Line the supply contract up with the connection date. A new or bigger connection needs a supply contract ready for the day it goes live, and a date that keeps moving makes that harder. Tell us your connection date and what capacity you’ve asked for, and we’ll get prices from suitable suppliers arranged early so the meter and contract are ready when the connection is. Start with our business electricity price comparison.
- Network charges are part of your bill. Our guide to non-commodity costs shows where network charges sit.
We welcome anything that gets the grid built and connected faster, because a grid that can carry cheaper power helps keep prices lower in the long run. We’ve covered the strain on the grid before, in our pieces on the Drax data centre and the Sea Link undersea cable. We’ll report the inquiry’s findings when Ofgem publishes them.