Ofgem parks eight transmission charging changes and sets dates for seven decisions in 2027

C

Charles Osborne

Contributor

Ofgem, the energy regulator, said on Friday 20 November 2026 that it will set aside eight proposed changes to the way electricity transmission charges are worked out, and gave dates in 2027 for decisions on seven others. It says a bigger redesign of the electricity market is coming and it doesn’t want “piecemeal changes” that could cut across it. No charge changes today. But two of the decisions due early in 2027 are about the balancing charge that is part of business electricity prices, and we can tell you now whether your contract fixes that charge or passes it on.

The facts

  • Who: Ofgem, in an open letter signed by Shai Hassid, Deputy Director for Electricity Charging and Market Design.
  • What: how Ofgem will prioritise proposals to change the rules for two charges. One is Transmission Network Use of System (TNUoS), the charge for using the high-voltage network. The other is Balancing Services Use of System (BSUoS), the charge for balancing the system.
  • Where the rules live: in the Connection and Use of System Code (CUSC). Companies in the industry can propose changes to it. Each proposal gets a number starting CMP, and Ofgem decides. Tap any CMP number in this story for a plain explanation of what it would change.
  • Decided today: nothing. The letter sets the order of work.
  • Highest priority: two urgent BSUoS changes, both due for decision in the first quarter of 2027.
  • Set aside: eight changes, four of them already with Ofgem for decision.
  • Late: Ofgem says several decisions it had planned for the 2027/28 charging year were not made, and it now intends to take them in time for 2028/29.

Why is Ofgem doing this?

The government is redesigning the electricity market through a programme called Reformed National Pricing (RNP). The letter says the Department for Energy Security and Net Zero is leading it, with support from Ofgem and the National Energy System Operator. RNP “will be the main route” for fundamental changes to transmission charging, using new powers proposed in the Energy Independence Bill once it becomes law.

Ofgem expects the lasting RNP arrangements “by the end of the decade”. Its argument is that a big change made now might last only a few years before being replaced. It warns that doing both could bring “avoidable implementation costs, increased charging volatility and uncertainty for market participants”.

So the letter says: “Proposed short-term changes to transmission network charging not aligned with the delivery of RNP will be deprioritised, unless they address an urgent and material defect”.

Ofgem’s top priority is something it calls legacy and transitional arrangements. These will decide “if and how existing assets transition from current charging arrangements” into the new system.

The three groups

1. Urgent, highest priority

  • CMP474: sets out when NESO can reset the balancing charge. Decision expected Q1 2027.
  • CMP475: would let NESO re-forecast the fixed balancing charge when market conditions change. Decision expected Q1 2027.

2. Going ahead, because they don’t clash with the reform

  • CMP316: transmission charges for power stations with more than one technology on one site. Q1 2027.
  • CMP397: the paperwork changes that follow from CMP316. Q1 2027.
  • CMP469: one more year of cost recovery for companies given new Grid Code duties. Q2 2027.
  • CMP453: billing the balancing charge on net flows for grouped sites that export. Q3 2027.
  • CMP445: a new generator pays transmission charges only for the part of its first year it is connected. Q3 2027.

Ofgem says more exact dates will follow on its website.

3. Set aside because of the reform

With Ofgem for decision:

  • CMP315: a review of a key input to the location-based part of transmission charges.
  • CMP375: a new way of calculating that same input.
  • CMP423: a change to the reference point the charging method uses.
  • CMP440: would let location-based demand charges go below zero.

Still being worked on by the industry:

  • CMP405: location-based charges or rewards for storage that imports at windy times.
  • CMP433: a new model for setting transmission charges by location.
  • CMP422: would let generators fix their transmission charges against NESO’s forecasts.
  • CMP460: a cap on what customers pay towards their transmission connection.

Ofgem adds a caution about this group: “Deprioritisation should not be interpreted as a view on the importance or merits of the underlying issues”.

Why were decisions late?

The letter says “competing priorities”, including an appeal against a code modification that Ofgem had to respond to, meant it could not make several decisions it had planned for the 2027/28 charging year. It says: “We are conscious this may have had an impact on stakeholders”.

The questions worth asking

  • What will the two urgent BSUoS changes do to bills? The letter gives their titles and a decision window. It doesn’t say what either would do to the charge.
  • What happens to demand charges by location? CMP440 would bring back TNUoS signals for demand by location. It is now set aside, and the question moves into RNP.
  • How long is “set aside”? Ofgem gives no date for returning to the eight. It expects the new arrangements by the end of the decade.
  • What will RNP mean for where a business is on the map? The letter doesn’t say. Ofgem expects “to provide further direction on RNP in early 2027”.
  • Does the Bill’s timing matter? RNP relies on powers in the Energy Independence Bill “once enacted”. The letter gives no date for that.

What does this mean for your business?

  • BSUoS and TNUoS are in your electricity price. Some contracts fix them for the term. Others pass them through, so your bill moves when the charge is reset. With two urgent BSUoS decisions due by the end of March 2027, send us your contract and we’ll tell you which kind you have.
  • Renewing in the next year? Ask the question up front. We get prices from suitable suppliers and show which charges are fixed in each quote. Arrange it as far ahead of your end date as you can. Start with our business electricity price comparison.
  • Generating or storing power on site? Several of the changes on Ofgem’s list are about generators, storage and co-located sites. Tell us what you have and we’ll show you which dates to watch.
  • See where these charges sit. Our guide to TNUoS and other non-commodity costs explains them, and the 16 November 2026 forecast for business electricity bills puts network charges at the centre of the rise.

We’ve written before about what the Energy Independence Bill means for business energy. We’ll report each decision as Ofgem makes it, starting with the two urgent ones.

Talk to our energy experts

Want to know whether your contract fixes network and balancing charges? Book an appointment with our Energy Team, get a quote, or call us on 01273 914000.

Book an appointment

Terms in this article

TNUoS (Transmission Network Use of System)
The charge for using the high-voltage electricity network. The rules for working it out are in the Connection and Use of System Code, and Ofgem decides on changes to them. Source: ofgem.gov.uk
BSUoS (Balancing Services Use of System)
The charge for balancing the electricity system. The National Energy System Operator (NESO) sets it, and it is part of business electricity prices. Source: ofgem.gov.uk
CMP474 (Fixed BSUoS Price Revision Mechanism)
A proposal to write into the rules a clear process for when NESO resets the balancing charge (BSUoS). NESO rates it high impact on suppliers. It is being handled as urgent, the proposal stage is finished and it is waiting for Ofgem's decision, due in the first quarter of 2027. Source: neso.energy
CMP475 (Amendment to the BSUoS tariff reset process)
A proposal to change the process for resetting the balancing charge (BSUoS). It would let NESO re-forecast the fixed tariff periods because of wider market conditions and, if needed, recover the financial position of its working capital fund. NESO says it will affect anyone affected by BSUoS, mainly suppliers. It is waiting for Ofgem's decision, due in the first quarter of 2027. Source: neso.energy
CMP316 (TNUoS Arrangements for Co-located Generation Sites)
A power station with more than one type of technology on the same site is called co-located. This proposal would set a way of working out transmission charges (TNUoS) for these sites that reflects their costs, because there are more and more of them. Source: neso.energy
CMP397 (Consequential changes required to CUSC Exhibits B and D to reflect CMP316)
The tidying-up that goes with CMP316. CMP316 changes one section of the code, and CMP397 changes two of the code's exhibits to match. Source: neso.energy
CMP469 (GC0186 Cost Recovery mechanism for CUSC Parties)
A separate rule change, numbered GC0186, puts new duties in the Grid Code on companies that are not contracted with NESO as Restoration Service Providers. CMP469 would extend by one year the mechanism that lets those companies recover their costs, so the new duties don't leave them out of pocket. NESO rates it high impact on suppliers and generators. Source: neso.energy
CMP453 (To Bill BSUoS on a net basis at BSC Trading Units)
The balancing charge (BSUoS) is billed gross. The proposal says that means customers grouped as a BSC Trading Unit pay it even when, taken together, they are exporting electricity at the connection point and so not using the system. CMP453 would bill those groups on their net flow. Source: neso.energy
CMP445 (Pro-rating first year TNUoS for Generators)
In its first year of connection, a generator would pay transmission charges (TNUoS) only from the date its charging starts, in proportion to the part of the year left. Source: neso.energy
CMP315 (TNUoS: Review of the expansion constant and the elements of the transmission system charged for)
The expansion constant is a key input in setting the part of transmission charges (TNUoS) that varies by location. This proposal would review how it is worked out so that it best reflects the costs involved. NESO rates it high impact on everyone who pays TNUoS. Source: neso.energy
CMP375 (Enduring Expansion Constant & Expansion Factor Review)
A proposal to change how the expansion constant and expansion factors are calculated, to better reflect growth of and investment in the national transmission system. The expansion constant is a key input in the part of transmission charges that varies by location. It was consulted on jointly with CMP315. Source: neso.energy
CMP423 (Generation-weighted Reference Node)
The charging method uses a reference node. Today it is weighted by demand. This proposal would weight it by generation. NESO's summary of the proposal says no more than that. Source: neso.energy
CMP440 (Re-introduction of Demand TNUoS locational signals by removal of the zero price floor)
The part of the transmission charge for demand that varies by location can't currently go below zero. This proposal would remove that floor for final demand, bringing back a price signal by location across Great Britain. To stop negative prices rewarding extra consumption, it would widen the period over which consumption is measured against negative tariffs. Source: neso.energy
CMP405 (TNUoS Locational Demand Signals for Storage)
Location-based demand charges are floored at zero. The proposal says that in areas dominated by wind and other intermittent generation there are significant benefits when storage imports electricity at times of peak wind. CMP405 would charge or reward storage that imports at times other than the Triads, for example when wind generation is running fully. Source: neso.energy
CMP433 (Optimised Transmission Investment Cost model (OpTIC))
A proposal to replace part of the model used to set transmission charges with an economic market model that reflects proposed network investment. The aim is charges that leave a company where it would expect to be in a wholesale market split into zones, with the best network investment assumed. NESO rates it high impact on suppliers, generators and demand customers. Source: neso.energy
CMP422 (Introducing the option to fix Generator TNUoS charges)
A proposal to give generators the chance to fix their wider transmission charges (TNUoS) against the tariffs NESO forecasts. Ofgem's letter numbers it CMP422. NESO lists the proposal with this title as CMP442. Source: neso.energy
CMP460 (Improving Transmission Connection Asset Charging)
A proposal to change how the assets that connect a customer to the transmission network are charged for. In its own words it seeks to 'socialise costs and cap customer contributions', to make the method more certain and fair. NESO rates it high impact on network owners, generators and demand customers. Source: neso.energy
GET IN CONTACT WITH US
Have a question about your energy strategy?

01273 914000

Free tools for your business

Get a Quote

Call Back Request

Book an Appointment

Update Contract End Date

Half Hourly Report Unsubscribe