Ofgem, the energy regulator, said on Friday 20 November 2026 that it will set aside eight proposed changes to the way electricity transmission charges are worked out, and gave dates in 2027 for decisions on seven others. It says a bigger redesign of the electricity market is coming and it doesn’t want “piecemeal changes” that could cut across it. No charge changes today. But two of the decisions due early in 2027 are about the balancing charge that is part of business electricity prices, and we can tell you now whether your contract fixes that charge or passes it on.
The facts
- Who: Ofgem, in an open letter signed by Shai Hassid, Deputy Director for Electricity Charging and Market Design.
- What: how Ofgem will prioritise proposals to change the rules for two charges. One is Transmission Network Use of System (TNUoS), the charge for using the high-voltage network. The other is Balancing Services Use of System (BSUoS), the charge for balancing the system.
- Where the rules live: in the Connection and Use of System Code (CUSC). Companies in the industry can propose changes to it. Each proposal gets a number starting CMP, and Ofgem decides. Tap any CMP number in this story for a plain explanation of what it would change.
- Decided today: nothing. The letter sets the order of work.
- Highest priority: two urgent BSUoS changes, both due for decision in the first quarter of 2027.
- Set aside: eight changes, four of them already with Ofgem for decision.
- Late: Ofgem says several decisions it had planned for the 2027/28 charging year were not made, and it now intends to take them in time for 2028/29.
Why is Ofgem doing this?
The government is redesigning the electricity market through a programme called Reformed National Pricing (RNP). The letter says the Department for Energy Security and Net Zero is leading it, with support from Ofgem and the National Energy System Operator. RNP “will be the main route” for fundamental changes to transmission charging, using new powers proposed in the Energy Independence Bill once it becomes law.
Ofgem expects the lasting RNP arrangements “by the end of the decade”. Its argument is that a big change made now might last only a few years before being replaced. It warns that doing both could bring “avoidable implementation costs, increased charging volatility and uncertainty for market participants”.
So the letter says: “Proposed short-term changes to transmission network charging not aligned with the delivery of RNP will be deprioritised, unless they address an urgent and material defect”.
Ofgem’s top priority is something it calls legacy and transitional arrangements. These will decide “if and how existing assets transition from current charging arrangements” into the new system.
The three groups
1. Urgent, highest priority
- CMP474: sets out when NESO can reset the balancing charge. Decision expected Q1 2027.
- CMP475: would let NESO re-forecast the fixed balancing charge when market conditions change. Decision expected Q1 2027.
2. Going ahead, because they don’t clash with the reform
- CMP316: transmission charges for power stations with more than one technology on one site. Q1 2027.
- CMP397: the paperwork changes that follow from CMP316. Q1 2027.
- CMP469: one more year of cost recovery for companies given new Grid Code duties. Q2 2027.
- CMP453: billing the balancing charge on net flows for grouped sites that export. Q3 2027.
- CMP445: a new generator pays transmission charges only for the part of its first year it is connected. Q3 2027.
Ofgem says more exact dates will follow on its website.
3. Set aside because of the reform
With Ofgem for decision:
- CMP315: a review of a key input to the location-based part of transmission charges.
- CMP375: a new way of calculating that same input.
- CMP423: a change to the reference point the charging method uses.
- CMP440: would let location-based demand charges go below zero.
Still being worked on by the industry:
- CMP405: location-based charges or rewards for storage that imports at windy times.
- CMP433: a new model for setting transmission charges by location.
- CMP422: would let generators fix their transmission charges against NESO’s forecasts.
- CMP460: a cap on what customers pay towards their transmission connection.
Ofgem adds a caution about this group: “Deprioritisation should not be interpreted as a view on the importance or merits of the underlying issues”.
Why were decisions late?
The letter says “competing priorities”, including an appeal against a code modification that Ofgem had to respond to, meant it could not make several decisions it had planned for the 2027/28 charging year. It says: “We are conscious this may have had an impact on stakeholders”.
The questions worth asking
- What will the two urgent BSUoS changes do to bills? The letter gives their titles and a decision window. It doesn’t say what either would do to the charge.
- What happens to demand charges by location? CMP440 would bring back TNUoS signals for demand by location. It is now set aside, and the question moves into RNP.
- How long is “set aside”? Ofgem gives no date for returning to the eight. It expects the new arrangements by the end of the decade.
- What will RNP mean for where a business is on the map? The letter doesn’t say. Ofgem expects “to provide further direction on RNP in early 2027”.
- Does the Bill’s timing matter? RNP relies on powers in the Energy Independence Bill “once enacted”. The letter gives no date for that.
What does this mean for your business?
- BSUoS and TNUoS are in your electricity price. Some contracts fix them for the term. Others pass them through, so your bill moves when the charge is reset. With two urgent BSUoS decisions due by the end of March 2027, send us your contract and we’ll tell you which kind you have.
- Renewing in the next year? Ask the question up front. We get prices from suitable suppliers and show which charges are fixed in each quote. Arrange it as far ahead of your end date as you can. Start with our business electricity price comparison.
- Generating or storing power on site? Several of the changes on Ofgem’s list are about generators, storage and co-located sites. Tell us what you have and we’ll show you which dates to watch.
- See where these charges sit. Our guide to TNUoS and other non-commodity costs explains them, and the 16 November 2026 forecast for business electricity bills puts network charges at the centre of the rise.
We’ve written before about what the Energy Independence Bill means for business energy. We’ll report each decision as Ofgem makes it, starting with the two urgent ones.
Talk to our energy experts
Want to know whether your contract fixes network and balancing charges? Book an appointment with our Energy Team, get a quote, or call us on 01273 914000.