A drone has clamped sensors onto a power line while the line was switched on and carrying electricity, in what SSEN Transmission says is a UK first. The company announced the work at Kintore Substation in Aberdeenshire on 16 November 2026, and Ofgem’s Chief Engineer was there to watch. No rule or price changes because of it. It is worth your time because it shows, in one small machine, how the grid can be made to carry more power without a single new pylon, and why that feeds through to what every business pays for electricity.
The facts
- Who: SSEN Transmission, which runs the high voltage network across the north of Scotland.
- Where: Kintore Substation, Aberdeenshire.
- What: a drone carried Dynamic Line Rating sensors up to an overhead conductor and attached them “while the circuit remains energised”.
- How many: around 32 sensors across two circuits, about 16 on each.
- Why it’s a first: the company calls it “the first successful drone installation of DLR technology onto a live transmission conductor in the UK”.
- The saving claimed: SSEN Transmission says its work to cut constraint costs saved consumers nearly £300 million in 2025/26, the year from April 2025 to March 2026. That figure covers all of its measures, not the drone or the sensors alone.
- What we don’t have: the cost of the Kintore work, the date of the flight, the make of drone, or a jobs figure. None of the sources we read gives them.
How the drone does it
SSEN Transmission describes three steps. The sensor is mounted on the drone. The drone flies it up to the conductor. The sensor is “remotely clamped into position before the drone returns to the ground”.

The point is what doesn’t happen. Nobody climbs the tower, no platform is driven into the field, and the line isn’t switched off.
Until now it was done the slow way. In March 2025 the company’s Innovation Portfolio Manager, Brant Wilson, wrote that sensors were “being fitted by teams using mobile elevated work platforms in the field, requiring short-term power outages”. He added a prediction: “as the technology evolves, it is likely that installation will be carried out by drones on live wires”. On our own count, that was 20 months before Kintore.
Why working on a live line matters
Switching off a transmission circuit to work on it is called an outage, and on a busy grid outages are hard to get. Martin Queen, Ofgem’s Chief Engineer, put it this way at Kintore:
“A live line installation is exceptionally important because it allows us to avoid having system outages, which in a highly constrained system are becoming increasingly difficult to take. So by moving to a live line system of operation and installation, we should be able to get these systems installed quicker and the consumer should be able to see the benefits and reduced costs in a much shorter timescale.”
Niall McDonald, project director at SSEN Transmission, said the approach “has the potential to make it easier and more flexible to deploy DLR across our network”. Modern Power Systems reported the company’s view that drones help most where getting an outage, or getting people physically to the line, would be difficult.
What the sensors are for
Every overhead line has a limit on the power it can carry. Push too much through and the cable heats up and sags. SSEN Transmission’s own description is that the limit is set so power can be carried “without making conductors sag beyond our safety standards”.
The traditional limit is a static rating: a fixed number for each season, based on cautious assumptions about the weather. Often the weather is kinder than the assumption, so the line could safely carry more than it is allowed to.
Dynamic Line Rating measures instead of assuming. SSEN Transmission says it uses “temperature, wind speed, solar radiation, and cloud cover to calculate the true, live capacity of overhead lines”. The chain works like this:
- sensors on the line read the conductor’s temperature
- the readings go to software that works out a live rating and a forecast rating
- those ratings go to NESO, the National Energy System Operator, which uses them when deciding how to balance generation and manage constraints
Wind is the neat part. Mr Wilson wrote: “the higher the wind speed, the better - as it cools conductors down, which in turn, allows us to increase the amount of power flowing through the line.” So the line can carry more when the wind is blowing, which is when wind farms have the most to send.
Where the money comes in
When the grid can’t carry all the power on offer, some generators have to be turned down or switched off. SSEN Transmission says this is “often renewable energy such as wind”, and that the costs are “ultimately met by electricity bill payers”.
The scale is large. First Secretary of State Louise Haigh told the CBI on 23 November 2026: “Last year, bill payers spent £2 billion switching off wind farms… While paying to switch on gas plants somewhere else.” We covered that speech in Minister targets European-level energy bills by mid-2030s.
Mr Wilson called the technology “relatively low-cost to install”. When Ofgem consulted on SSEN Transmission’s first scheme in June 2022, the working assumption was one sensor about every 7.5km, or roughly 21 sensors for about 154km of line. The company told Ofgem that extending the scheme along a second section of line would cost less than £1 million more, because most of the cost sat in the control system and extra monitoring points were “relatively inexpensive”.
Where this has been tried before
Kintore is the second step. The first was north of Beauly, on the 275 kV lines up to Dounreay in Caithness.
- Why there: a large amount of wind generation is contracted to connect in Caithness. SSEN Transmission’s funding application said “it is expected that there will be significant network constraints in the area from 2024”.
- The numbers in 2022: Ofgem’s consultation recorded 1,111 MW of generation connected in the Caithness area and a further 2,714 MW scheduled to connect, most of it onshore wind.
- The timeline: Ofgem accepted the need for the scheme in 2022. By March 2025, 42km had been fitted. By June 2025 the sensors were on more than 300km of line across ten circuits, which the company called the biggest such network in the UK. In September 2026 it announced the system had gone live.
- The promise made then: that it was “working towards implementing live-line drone installation” as the technology moved to other parts of the network. Kintore is that promise kept.
The limits
SSEN Transmission doesn’t oversell it. Its 16 November statement says: “Network upgrades will ultimately deliver the greatest increase in capacity, but DLR can provide an additional boost.” Modern Power Systems reported that the company sees the technology as a complement to new lines and not a replacement for them.
That matches what the company told Ofgem about Beauly. The sensors were a short-term measure to ease constraints ahead of reinforcement, with the long-term answer being “new and upgraded electricity network infrastructure”. We reported on two of those upgrades on 19 November 2026 in Two 400kV substations approved after council refusals.
The questions worth asking
- How much extra power can the Kintore circuits carry with the sensors on? Not stated.
- How much of the £300 million came from Dynamic Line Rating? The figure is for all of SSEN Transmission’s constraint-cutting work. No source splits it.
- Where next? The company says “other suitable locations on its network” and names none.
- Will the other network owners follow? Mr Wilson wrote in March 2025 that the best result would be the three transmission operators in Great Britain working together, led by NESO, so that NESO gets “one consistent set of data”. We haven’t seen a plan for that.
- Is it really a first? That is SSEN Transmission’s claim. Every report we read rests on the company’s announcement.
What does this mean for your business?
- You pay for a congested grid whether you see it or not. Constraint costs are met by bill payers, in SSEN Transmission’s own words, and that includes businesses. Anything that lets an existing line carry more wind power on a windy day takes a little of that cost away. Our take: we welcome it. Getting more out of the cables already hanging there is about the cheapest extra capacity the grid can find.
- Don’t expect it on next month’s bill. A sensor on a line in Aberdeenshire doesn’t change a contract price in Brighton. The size of the saving that reaches any one business isn’t in any source we read, and we won’t put a number on it.
- Find out how these costs reach you. Some contracts fix system and network costs into the unit price. Others pass them on as they change. Send us your contract or your latest quote and we’ll go through with you which of your costs are fixed and which can move.
- Buy on the prices in front of you, and buy early. SSEN Transmission itself calls the sensors a boost alongside new lines, not a substitute for them. Your next contract will be priced on the grid as it is when you sign. Get business electricity prices from suitable suppliers as far ahead as you can, so you’re choosing your moment.
- Planning a new connection or more capacity? Ofgem has opened an inquiry into how long connections take. Our story, Ofgem opens urgent inquiry into grid connection delays, has the detail, and we’ll price the supply for the date you need it.
Talk to our energy experts
Want to know which grid costs are fixed in your electricity price and which can change? Book an appointment with our Energy Team, get a quote, or call us on 01273 914000.