The government set the budget for its next renewables auction on Thursday 19 November 2026, and the figure is a notional £1 for each of the wind and solar groups. That isn’t the real budget. Ministers will look at every wind and solar bid, with the bidders’ names removed, and only then decide how much to spend. The auction is Allocation Round 8 (AR8) of the Contracts for Difference (CfD) scheme, and the cost of that scheme is charged through electricity bills. Your bill doesn’t change today. What your business pays when the results come depends on how your contract treats CfD costs, and that is something we can check for you now.
The facts
- Who: the Department for Energy Security and Net Zero (DESNZ), which gave the budget notice to the National Energy System Operator, the auction’s delivery body.
- What: the Contract Budget notice for AR8. The round opened to applications on 20 July 2026.
- The budget: £1 a year for each of four groups of technologies, which the notice calls pots. Pot 1 is solar. Pot 2 is onshore wind and remote island wind. Pot 3 is offshore wind. Pot 4 is floating and other deepwater offshore wind.
- Why £1: the notice says it means “no projects will clear under the initial budget and all bids will be viewed anonymously”.
- The test: “Budget will only be provided if bid prices are in consumers’ interests. If this condition is not met, we will not provide budget.”
- Who decides: final budgets “will be made in conjunction with HM Treasury” and will be published alongside the results.
- Years covered: the budget table runs from 2028/29 to 2033/34.
- No size limits: no capacity caps apply to any pot, and there are no minimum or maximum amounts for any technology.
What is a Contract for Difference?
A CfD is a fixed-price deal for a generator such as a wind or solar farm. The generator is guaranteed a set price, called a strike price, for each megawatt hour (MWh) of electricity. When the market price is lower, the generator is topped up. When it is higher, the generator pays the difference back. Electricity suppliers pay for the scheme through a compulsory levy, which is why it shows up in what businesses and households pay. Our guide to non-commodity costs shows where it sits on a bill.
What’s different about this auction?
In the last round, AR7, the government looked at offshore wind bids before settling that budget. DESNZ says that round “secured a record amount of offshore wind at a price 40% cheaper than the alternative of building and operating new gas power plants”.
AR8 is the first round where that applies to several technologies. The accompanying note says: “This is the first round where bid stack visibility will apply to multiple technologies, extending across solar and wind technology pots.”
Once bids are in, contracts go “to the cheapest eligible projects first”, as long as they fit within the final budget.
Energy Minister Michael Shanks said: “These reforms build on that progress by making the auction process more transparent and competitive, so we secure the best projects at the best price for consumers while accelerating the transition to clean power.”
Exchequer Secretary to the Treasury Dan Tomlinson said: “Our new approach to this renewables auction maximises transparency and control over what we buy, ensuring we get the clean power we need at the right price.”
No money for tidal, wave or energy from waste
Pot 5 has a budget of £0, and that one is final. It covers advanced conversion technology, anaerobic digestion, dedicated biomass with combined heat and power (CHP), energy from waste with CHP, geothermal, hydro, landfill gas, sewage gas, tidal stream and wave power.
The notice says: “The Government will not allocate budget to Pot 5 technologies in this round.” The accompanying note says the expected effect is that “no assets will be supported in this pot”, and that the decision “reflects AR8’s focus on strategic technologies which can deploy at scale and at lower cost in the near term”.
The administrative strike prices
The notice lists an administrative strike price (ASP) for each technology. They are unchanged from AR7. In the government’s words, ASPs “are a technical construct and do not represent the Government’s central view of the cost of each of these technologies”, and competition “should deliver clearing prices below ASPs”.
- Solar: £75 per MWh
- Onshore wind: £92 per MWh
- Offshore wind: £113 per MWh
- Floating offshore wind: £271 per MWh
These are in “2024 prices”, which means the amounts are stated as money was worth in 2024, before the inflation since. The notice gives a figure of 1.0762 to bring them up to September 2026. On our own maths that makes solar about £80.72, onshore wind about £99.01 and offshore wind about £121.61 per MWh.
Scottish offshore wind projects will have a separate clearing price from English and Welsh ones. The note says this is “to reduce the risk that annual fluctuations in distribution and transmission network charges lead to significant overcompensation for some projects”.
The questions worth asking
- What counts as good value? The government says budget only follows if bid prices “are in consumers’ interests”. Its July notice said “internal metrics” will be used to decide. Those haven’t been published.
- How much will be bought? Nobody outside government knows yet. The July notice warned: “It should not be inferred that there will be increases to Budgets in this or future rounds.”
- What will it do to bills? The note is careful here. The final budget will be “an estimate of maximum annual support in the first five years following deployment”. It “is not the actual cost of the subsidy”, which depends on clearing prices and future wholesale prices. It also “differs from the net impact of AR8 on energy bills”.
- What happens to the technologies in Pot 5? They get nothing this round. The announcement doesn’t say what comes next for them, beyond “more substantial reforms for Allocation Round 9”.
- When are the results? No date is given in the notice or the announcement.
What does this mean for your business?
- CfD costs sit in your electricity price whether you can see them or not. Some contracts fix them inside the unit rate. Others pass them through at cost, so the charge moves when the levy does. Send us your contract and we’ll tell you which you have.
- The budget table starts in 2028/29, so that is the first year a project from this round counts as a cost. A contract you sign now may still be running then. If yours passes CfD costs through, the outcome of this auction lands on you. That is a reason to settle the question when you arrange the contract, well ahead of your end date, and we’ll put it to suitable suppliers for you.
- Compare quotes on the same footing. A lower unit rate with levies passed through isn’t the same offer as a higher rate with everything fixed. When we compare business electricity prices for you, we show which charges are fixed in each quote.
We covered the £12 billion Vanguard wind farms, backed by the previous round, in £12bn Norfolk offshore wind farms get the go-ahead. We’ll report the AR8 results and final budgets when they’re published.
Talk to our energy experts
Want to know how much of your electricity price is CfD and other levies? Book an appointment with our Energy Team, get a quote, or call us on 01273 914000.