Yorkshire Water is spending £2.6 million at Kilham sewage treatment works, near Driffield in East Yorkshire, to build an 800m² aerated rush bed. The planted wetland will give storm water extra treatment in heavy rain, cutting how often the works discharges into the local watercourse. Yorkshire Water announced the scheme on 25 November 2026, and contractor Mott MacDonald Bentley starts on site on Monday 30 November. The works keeps running throughout, so nothing changes for local customers while it’s built.
The cold hard facts
- Who: Yorkshire Water, with contract partner Mott MacDonald Bentley.
- What: an 800m² aerated rush bed next to the existing works, plus new pumps, monitoring and sampling equipment, aeration blowers, pipework and controls.
- Capacity: it can treat up to 11.6 litres of storm water a second, Yorkshire Water says. On our own maths, that’s about 41,800 litres an hour at full flow.
- Where: Kilham, East Yorkshire.
- Cost: £2.6 million.
- When: announced 25 November 2026; work starts 30 November. No finish date was given in the sources we read.
- Flood protection: the rush bed will be raised up to protect it from flood risk.
- Jobs: not given.
How a rush bed works
Yorkshire Water says the bed “uses plants alongside an aeration system to help naturally treat storm water as it passes through the wetland.” It’s a nature-based solution: instead of more concrete tanks, the plants and pumped air do part of the cleaning.
The design reuses the site’s existing storm tanks, so less has to be built new.
Liam Thomas, project manager at Yorkshire Water, said: “By introducing a nature-based solution alongside our existing treatment processes, we can provide additional treatment during periods of heavy rainfall and reduce pressure on the treatment works.”
Part of a national trial
Yorkshire Water says the scheme is part of “an Environment Agency and Defra-approved trial exploring the use of Treatment Wetlands to reduce storm discharges and groundwater entering the sewer network.” Great Driffield Radio carried the same details.
Our take: that makes Kilham a test case. If the wetland works here, it could be a way to cut spills with less new concrete at other small works.
It also sits inside bigger numbers. Yorkshire Water is investing over £8.3 billion across Yorkshire from 2025 to 2030, including £1.5 billion to reduce storm discharges. On 23 November it also started a £63m storm overflow programme in Huddersfield.
The questions worth asking
- How many fewer spills? Yorkshire Water hasn’t given a target for Kilham.
- When does it finish? No completion date has been published.
- Who judges the trial? The Environment Agency and Defra approved it. Neither source says when or how results will be reported.
What does this mean for your business?
- Farms and rural firms near Kilham. Our take: if your business relies on the local watercourse, for livestock, irrigation or tourism, cleaner discharges are good news. Construction starts Monday, so expect site traffic.
- You’re paying for this through wastewater charges. Send us a recent bill and we’ll show you how your water, wastewater and drainage charges split, and whether they look right for your site.
- Choose who bills you. Yorkshire Water runs the works, but a business in England can choose its water retailer. We compare business water deals and handle the switch.
- Sort the contract early. Arrange your water and energy contracts as far ahead as you can, so you’re choosing with time on your side.
We’ve also covered the Ofwat overhaul of the water sector and the April 2026 water rate rises.
Talk to our energy experts
Want to know what your water and wastewater charges are really for? Book an appointment with our team, get a quote, or call us on 01273 914000.