United Utilities finishes £2m Appleby sewer upgrade Skip to content
A round settling tank at a water treatment works under a cloudy sky.
Water 4 min read

United Utilities completes Appleby sewer upgrade as £2m river work moves to Clifton

C

Charles Osborne

Contributor

United Utilities has finished sewer work in Appleby, Cumbria, and is now building extra storage in nearby Clifton. The two schemes cost around £2 million between them, and both aim to cut how often storm overflows spill into local rivers in heavy rain. Appleby’s work feeds the River Eden and Clifton’s the River Lowther. The Clifton scheme is due to finish in December 2026. Nothing is compulsory for businesses, but the work is a clear example of where the sewerage part of a water bill goes.

The facts

  • Who: United Utilities, the water and wastewater company for the North West, with construction partner Cubby at Appleby.
  • What: a new overflow chamber, a screen and a bigger local sewer in Appleby, now complete. 34 cubic metres of extra stormwater storage in Clifton, under construction.
  • Where: Appleby and Clifton, in the Eden area of Cumbria.
  • How much: “around £2 million” across both schemes, in the company’s words. It doesn’t split the cost between the two.
  • When: Appleby is done. Clifton “is expected to be completed by December 2026”.
  • Why: to “reduce the frequency with which the local storm overflow operates during periods of heavy rainfall” and improve water quality in the River Eden and River Lowther.

What was built in Appleby

United Utilities says the Appleby project installed a new overflow chamber and screen and increased capacity in the local sewer network. Its page for the scheme gives the detail. It replaced the old storm overflow chamber with a tank measuring 4.8m by 3.1m by 1.6m, which “stores storm water when we have heavy rainfall, preventing our system from being overloaded.” On our own maths, those measurements multiply to about 23.8 cubic metres.

The company also upsized a pipe, which it says gives “10m3 of additional storage”. The screen inside the tank stops debris and unflushable items passing through the overflow in a storm.

The work was in the town centre. Stephen Capstick, Delivery Manager for United Utilities, said: “The Appleby scheme has been challenging due to its town centre location, and we’d like to thank residents, businesses and road users for their patience while we completed the work.”

As the job finished, United Utilities and Cubby gave £250 each, £500 in all, towards Appleby’s Christmas lights.

What is being built in Clifton

At Clifton, engineers are installing 34 cubic metres of extra stormwater storage. On our own maths, that is 34,000 litres. United Utilities says it is “designed to improve network performance during wet weather” and will help improve water quality in the River Lowther by reducing storm overflow operations.

The bigger programme

Both schemes sit inside what United Utilities calls the largest investment programme in its history. It says it will invest “more than £13 billion before 2030 to protect and enhance rivers, lakes and bathing waters across the North West”. Its Appleby page calls this the Big North West Upgrade and says it covers “over 500km of rivers, lakes and bathing waters”.

The Cumberland and Westmorland Herald, the local paper for the area, reported the Appleby completion under the line: “Sewer upgrades worth £2m aim to cut storm overflow spills into two Eden rivers.”

The questions worth asking

  • How many spills will this stop? Neither United Utilities nor the Herald gives a figure for how often the Appleby or Clifton overflows operated before, or how often they will after.
  • How is the £2 million split? The company gives one figure for both schemes.
  • Will Clifton finish on time? The target is December 2026. We’ll check.
  • How does this feed into bills? The company’s update doesn’t say.

What does this mean for your business?

  • This is where your sewerage charge goes. In our April 2026 water rates story we set out United Utilities’ rises: 17.9% on water, 8% on sewerage and 11.1% on trade effluent. Our take: a £13 billion programme has to be paid for, so North West businesses should budget for wastewater costs that keep climbing. Send us your bills and we’ll show you what you pay for each part.
  • Discharging to sewer? Check your trade effluent charges. If your site sends process waste to the sewer, that is billed on its own. Ask us to check the volumes and rates on your bill are right.
  • Sort the contract early. In England a retailer bills your business for water, and you can choose it. Get your business water arrangements in place as far ahead as you can, so you are choosing with time on your side.

We covered Bristol Water lifting its hosepipe ban on 25 November 2026 in Bristol Water lifts hosepipe ban but drought goes on.

Talk to our water experts

Want someone to go through your water and wastewater bill? Book an appointment with our team, get a quote, or call us on 01273 914000.

Book an appointment

Terms in this article

Storm overflow
A relief point in the sewer network. When heavy rain would overload the system, it lets rainwater mixed with sewage spill into a river or the sea. United Utilities describes overflows as a pressure relief valve that protects homes and businesses from flooding. Source: unitedutilities.com
Stormwater storage
Tanks or larger pipes that hold rainwater and sewage during a storm, so less of it has to spill through an overflow. The water is held back and treated once the rain eases. Source: unitedutilities.com
Screen
Equipment inside an overflow that stops debris and unflushable items, such as wet wipes, passing into the river when the overflow operates. Source: unitedutilities.com
Trade effluent
Liquid waste from a business process that a business sends to the public sewer. Water companies set a separate rate for it alongside standard sewerage. Source: blacksheeputilities.co.uk
GET IN CONTACT WITH US
Have a question about your energy strategy?

01273 914000

Free tools for your business

Get a Quote

Call Back Request

Book an Appointment

Update Contract End Date

Half Hourly Report Unsubscribe